Quality in Multi-Apartment Building Modernization
Published on 21 June 2018
Lithuania
This is the good practice's implementation level. It can be national, regional or local.
About this good practice
The following measures where implemented:
- technical projects are checked and approved by municipalities specialists;
- construction companies are required to provide insurance, that they can perform works in accordance to the contract;
- construction companies are pre-checked before public procurement process (companies are checked for their capacity, excluded companies in black list);
- construction works are supervised by independent and certified specialists;
- effective complaint system is developed in order to timely react to any resident complaint;
- BETA (technical support agency)performs on-site visits to check all requirements are met;
- state territorial planning and construction inspectorate (local construction supervisory authority) has to visit each construction site at least 2 times;
- good examples of implemented projects are promoted in the media.
- technical projects are checked and approved by municipalities specialists;
- construction companies are required to provide insurance, that they can perform works in accordance to the contract;
- construction companies are pre-checked before public procurement process (companies are checked for their capacity, excluded companies in black list);
- construction works are supervised by independent and certified specialists;
- effective complaint system is developed in order to timely react to any resident complaint;
- BETA (technical support agency)performs on-site visits to check all requirements are met;
- state territorial planning and construction inspectorate (local construction supervisory authority) has to visit each construction site at least 2 times;
- good examples of implemented projects are promoted in the media.
Resources needed
Buildings affected:
- buildings renovated (as of 9 September 2016) – 848
- estimated surface (m2) affected - ~ 1.5 million
Indicators above are related to other practices as well, specific allocation to this GP is not possible.
- buildings renovated (as of 9 September 2016) – 848
- estimated surface (m2) affected - ~ 1.5 million
Indicators above are related to other practices as well, specific allocation to this GP is not possible.
Evidence of success
Introduced measures resulted in major increase in project pipeline. The GP helped to shape Financial instruments in a way so they become attractive to final beneficiaries.
Supervision measures helped to increase quality of construction works and satisfaction among final beneficiaries.
Supervision measures helped to increase quality of construction works and satisfaction among final beneficiaries.
Potential for learning or transfer
Partners may need to adjust various legislation acts to implement provided measures.
Measures may vary depending on the region weather conditions.
Measures may vary depending on the region weather conditions.