The thermal rehabilitation of blocks of flats in Iasi City for energy efficiency increase
Published on 03 January 2019
Romania
Nord-Est
This is the good practice's implementation level. It can be national, regional or local.
About this good practice
The thermal rehabilitation of 4 blocks of flats, situated in the city center in Iasi, Romania (Piata Unirii 7-11 and Str V. Alecsandri). These were old buildings, from the ’60-‘70s, highly degraded and energy consuming, with pipes networks for utilities and some parts seriously affected by the weather during the time (rooftop and basement, some parts of walls, windows frames). The inhabitants of the apartments inside these blocks of flats complained all the time about the high cost caused by these malfunctions and about the ugly aspect of the buildings. The municipal project supported investments in energy efficiency renovation of the housing blocks in the city center of Iasi for families with an average income below 350 Euros/month.
The technical project included enveloping facades with insulating material, changing exterior carpentry with PVC windows with double glazing, upper terrace of the building restoration and upgrading of district heating in the basement, where appropriate.
Funding work have been advanced by the Municipality, costs being shared between the Municipality, the Owners Associations and Government budget through European funds, which are also the main stakeholders, Main beneficiaries are the inhabitants of these blocs of flats, about 480 people.
The technical project included enveloping facades with insulating material, changing exterior carpentry with PVC windows with double glazing, upper terrace of the building restoration and upgrading of district heating in the basement, where appropriate.
Funding work have been advanced by the Municipality, costs being shared between the Municipality, the Owners Associations and Government budget through European funds, which are also the main stakeholders, Main beneficiaries are the inhabitants of these blocs of flats, about 480 people.
Resources needed
about 1.940.000 lei including VAT
Evidence of success
increased energy efficiency resulting increased quality of services/quality of life, with lower cost and an improved aspect of the building; decrease of utilities costs between 10% to 30% (mainly during winter); increased safety of the buildings
Potential for learning or transfer
This practice has a high potential to be transferred, mainly to East European Countries, which have the same "communist" architecture specificity (block of flats) with similar issues